This project aims to upgrade the Fierza substation with a new 400/220 kV phase-shift transformer and construct a new 400 kV interconnection with Kosovo. The investments include the following measures: 1) Construction of a new 400/220/110 kV substation near the Fierza substation; 2) Installation of a 400/220kV, 600 MVA phase shift transformer; 3) Identification and implementation of control, protection, monitoring, telecommunication and other measures to digitalise the Fierza substation; 4) Reconfiguration of 220 kV and 400 kV lines connecting to this substation; 5) Connection to existing interconnections 400 kV Koman – Kosova B and 220 kV Fierza – Prizren 2; 6) Connection to 110 kV transmission grid in the area; 7) Construction of a new 400 kV interconnection line between 400/220 kV Fierza substation and 400 kV Prizren 4 substation in Kosovo with ACSR 2x490/65 mm2 conductor (25 km in Albania).
The WBIF provides technical assistance for developing the feasibility study and environmental and social scoping for the project.
WBIF | Grant | WB31-ALB-ENE-02 | € 478,018 |
EBRD | Loan | € 35,200,000 | |
National Contribution | Own Contribution | € 5,000,000 | |
Anticipated WBIF Grant | External Grant | € 14,340,000 | |
Total | € 55,018,018 | ||
Total Grants | € 478,018 | ||
Total Loans | € 35,200,000 |